Category Archives: Hermiston Irrigation District

GOOD NEWS

Our repairs are holding, the dams have been removed, we are turning up the A~Line Canal, opening the MA~Line and charging the rest of the system. Thank you for your support. Let’s have a great irrigation season.

Posted in Hermiston Irrigation District | Comments Off on GOOD NEWS

In Other News

C&E Trenching has completed construction on HID’s new pump station where the Tail of the A-Line merges into the Maxwell Canal. This project was funded by FEMA and Oregon Emergency Management. This pump station was built to mitigate for a … Continue reading

Posted in Hermiston Irrigation District | Comments Off on In Other News

M Line Repair

The repairs to the M Line were completed over the weekend and the water was released on Monday morning to charge this line. However, after water was released, the M Line broke in a different location further upstream. HID immediately … Continue reading

Posted in Hermiston Irrigation District | Comments Off on M Line Repair

Update April 12, 2024

Repairs to the M-Line are on schedule. Crews are pouring concrete this morning. We are also releasing 92 cfs from Cold Springs Reservoir and charging up the rest of the system so that dry areas will charge up quickly when … Continue reading

Posted in Hermiston Irrigation District | Comments Off on Update April 12, 2024

Barton & Minnehaha Pump Stations and Angus Acres Line

The Barton and Minnehaha Pump Station’s as well as the Angus Acres Line have been started.

Posted in Hermiston Irrigation District | Comments Off on Barton & Minnehaha Pump Stations and Angus Acres Line

Grant Funding Opportunity

Posted in Hermiston Irrigation District | Comments Off on Grant Funding Opportunity

Active Lines

The following areas have irrigation water running: The A-Line, the Upper end of Maxwell Canal on the west end of town, the B-Line, the D-Line, the G-Line, I-Line, the R-Line and connecting Z-Line. The L and LA Lines are expected … Continue reading

Posted in Hermiston Irrigation District | Comments Off on Active Lines

System Wide Update:

There is a major break on the M-Line near Ott Rd & Moe Ln. Crews worked on this area for weeks during the maintenance season, but the 100 year old concrete pipe failed. Crews and professional consultants will be working … Continue reading

Posted in Hermiston Irrigation District | Comments Off on System Wide Update:

Z Line

Crews have started the Z Line this afternoon. See insights and ads Boost post Like Comment Share

Posted in Hermiston Irrigation District | Comments Off on Z Line

G Line

Water has been turned into the G Line and is now charging.

Posted in Hermiston Irrigation District | Comments Off on G Line